== Day 1: 9 Jan 2012 == | == Day 1: 9 Jan 2012 == | ||
− | Jacob worked on the Kinect all day. David set up the EEE PC and wrote some code. Josh and Logan hacked the Arduino and made some Solidworks models. We all worked on the pegbot. Martin was not yet back. | + | Jacob worked on the Kinect all day. David set up the EEE PC and wrote some code. Josh and Logan hacked the Arduino and made some Solidworks models. We all worked on the pegbot. Martin was not yet back. Checkoff 1 was completed later in the day. Deans connectors were installed to protect the battery and make battery swaps easy. We implemented a modular motor connector. |
− | + | ||
− | Checkoff 1 was completed later in the day. Deans connectors were installed to protect the battery and make battery swaps easy. | + | |
== Day 2: 10 Jan 2012 == | == Day 2: 10 Jan 2012 == | ||
Jacob started working on color recognition for the Kinect. Logan's jellyfish were delivered. David finished removing the GUI from the EEE PC. Josh completed checkoff 2 using a short-range IR sensor. Martin worked in Solidworks all day. | Jacob started working on color recognition for the Kinect. Logan's jellyfish were delivered. David finished removing the GUI from the EEE PC. Josh completed checkoff 2 using a short-range IR sensor. Martin worked in Solidworks all day. | ||
+ | |||
+ | == Day 3: 11 Jan 2012 == | ||
+ | |||
+ | We established serial communication between the Arduino and the laptop. Logan worked on motion control code. |
Revision as of 18:13, 11 January 2012
Contents |
Day 0: 8 Jan 2012
Discovered the wiki.
Day 1: 9 Jan 2012
Jacob worked on the Kinect all day. David set up the EEE PC and wrote some code. Josh and Logan hacked the Arduino and made some Solidworks models. We all worked on the pegbot. Martin was not yet back. Checkoff 1 was completed later in the day. Deans connectors were installed to protect the battery and make battery swaps easy. We implemented a modular motor connector.
Day 2: 10 Jan 2012
Jacob started working on color recognition for the Kinect. Logan's jellyfish were delivered. David finished removing the GUI from the EEE PC. Josh completed checkoff 2 using a short-range IR sensor. Martin worked in Solidworks all day.
Day 3: 11 Jan 2012
We established serial communication between the Arduino and the laptop. Logan worked on motion control code.