Day 1
Productive things: shop training completed. Not so productive things: trying to get maple to work
Day 2
Got maple to run a program. *round of high fives* The problem was that we couldn't change the serial port, because maple was not being recognized by the tablet. Useful link here if you're having trouble: http://forums.leaflabs.com/topic.php?id=73#post-788. Completed most of the wiring for the kitbot. Later in the evening the whole team attended the solidworks workshop.
Day 3
Completed wiring for kitbot and got started on some solidworks sketches.