Line 29: | Line 29: | ||
*calibrated our sensors partially | *calibrated our sensors partially | ||
*wrote test program for testing kit bot | *wrote test program for testing kit bot | ||
+ | |||
+ | ===== Day 4 (1/9) ===== | ||
+ | *calibrated ir sensors | ||
+ | *fitted IR sensor data | ||
+ | *gyroscope hooked up | ||
+ | *got communication between edison and gyroscope | ||
+ | *kit bot drives around avoiding walls |
Revision as of 21:05, 10 January 2015
Contents |
Week 1
Day 0 (1/5)
- Brainstormed multiple methods of picking up and sorting blocks
- Brainstormed drive train ideas
- got started with edison
- successfully ran some sample programs
- began cadding ideas
Day 1 (1/6)
- Created state machine outline
- Created general software outline
- Received shop training
- Began working with sensors on Edison
- Soldered voltage regulator to battery pack for use with Edison
Day 2 (1/7)
- assembled servo shield and mounted on Edison
- successfully captured color video with camera with OpenCV
- printed kit bot and began assembly
- fixed voltage regulator
- Tested motors with motor controller
Day 3 (1/8)
- fully assembled kit bot with wiring
- got kit bot moving
- calibrated our sensors partially
- wrote test program for testing kit bot
Day 4 (1/9)
- calibrated ir sensors
- fitted IR sensor data
- gyroscope hooked up
- got communication between edison and gyroscope
- kit bot drives around avoiding walls