Monday, 1/3/2011
+
01.03.2011
-
Team 13 will be operating at half-power for the first week; Kevin and Bayley are both due to arrive by the beginning of week two.
+
'''tl;dr''': Team 13 is operating at half-power for the first week; Kevin and Bayley will join us starting next Monday. Dima and Rebecca are working extra hard to meet the Checkpoints and be ready for Mock Contest 1.
'''Current progress''': Absentees aside, we nonetheless completed Checkpoint 1 by the deadline. Pegbot is now capable of 1) moving in a circle or in a straight path and 2) communicating with eeePC via Bot Client.
'''Current progress''': Absentees aside, we nonetheless completed Checkpoint 1 by the deadline. Pegbot is now capable of 1) moving in a circle or in a straight path and 2) communicating with eeePC via Bot Client.
-
'''Future direction''': Strategy discussion. Rebecca is studying what former groups have done, what has worked, what hasn't, etc. Our choice of strategy will likely dictate (and in turn, also be dictated by) the hardware details of our robot. Team 13 would like to receive input from all members, so efforts are being made to hold a real-time discussion with Kevin and Bayley. Dima is being trained in use of the laser cutter.
+
'''Future direction''': Strategy discussion. Rebecca will study what former groups have done, what has worked, what hasn't, etc. Our choice of strategy will likely dictate (and in turn, also be dictated by) the hardware details of our robot. Team 13 would like to receive input from all members, so efforts are being made to hold a real-time discussion with Kevin and Bayley. Dima hopes to have finished our robot by the end of the week.
 +
 
 +
----
 +
01.04.2011

Revision as of 17:40, 4 January 2011

01.03.2011

tl;dr: Team 13 is operating at half-power for the first week; Kevin and Bayley will join us starting next Monday. Dima and Rebecca are working extra hard to meet the Checkpoints and be ready for Mock Contest 1.

Current progress: Absentees aside, we nonetheless completed Checkpoint 1 by the deadline. Pegbot is now capable of 1) moving in a circle or in a straight path and 2) communicating with eeePC via Bot Client.

Future direction: Strategy discussion. Rebecca will study what former groups have done, what has worked, what hasn't, etc. Our choice of strategy will likely dictate (and in turn, also be dictated by) the hardware details of our robot. Team 13 would like to receive input from all members, so efforts are being made to hold a real-time discussion with Kevin and Bayley. Dima hopes to have finished our robot by the end of the week.